Wednesday, June 11th, 2025

City learns wastewater plant needs $32M upgrade

By William Kincaid
CELINA - The City of Celina needs to make a staggering $32 million in improvements at the wastewater treatment plant in order to eliminate overflows or bypasses into Beaver Creek and maintain its National Pollutant Discharge Elimination System permit with the Ohio EPA.
City councilors learned more about what it will take to expand the wastewater treatment plant and increase capacity from Jones & Henry Engineers LTD of Toledo during a utilities committee meeting this week.
They also were informed that the most likely avenue for financial assistance to undertake the dauntingly expensive project is the Water Pollution Control Loan Fund administered by the Ohio EPA.
Excessive infiltration and inflow reduces wastewater treatment capacity during periods of heavy rain. When the plant cannot handle the high flow rate, influent bypasses directly into Beaver Creek. The plant has about seven bypasses a year. The bypasses average about 1 million gallons but have been as large as 7.7 million gallons.
Councilors in 2023 moved to authorize a $174,000 agreement with Jones & Henry Engineers for review of the city's National Pollutant Discharge Elimination System permit and to perform an analysis of the wastewater treatment plant.
"In your guys' permit, there is what's called the compliance schedule … and that's orders from the EPA," explained Peter Latta, director of the engineering firm's Toledo office. "Those orders direct you to complete an NFA, which is a No Feasible Alternative."
The NFA, he said, is a report that studies the city's wastewater treatment plant and sewers and identifies means of eliminating bypasses. The NFA was submitted to the Ohio EPA in April.
"Following the completion of that, their expectation is that you proceed into the design of some improvement to eliminate this bypass," he continued.
Ohio EPA had initially wanted Celina to submit a permit to install for plant improvements in April 2026 and for construction to begin six months later in October. But Jones & Henry believe they have bought the city a little extra time.
"We requested a modified schedule because that schedule is a little aggressive, and we don't feel that in your guys' best interest you wanted to execute that schedule," Latta said. "So we proposed about a six-month delay in that. As of right now, the EPA has not objected to that revised schedule."

The plant
The wastewater plant underwent an expansion that was completed in January 1991. Since that time, one improvement was made in 1993, according to Troy Brehmer, the engineering firm's director of wastewater treatment.
"Some of the equipment is nearing the end of its useful life, and that equipment needs replaced," Brehmer said. "The structure is acceptable for continued operation, the mechanisms need replaced."
The plant is designed to process 3 million gallons a day (mgd) but has a wet weather rating of 8 to 10 mgd. The plant's overall rating needs bumped up to 4.25-4.5 mgd and its wet weather rating to 22 mgd, in order to eliminate bypasses to Beaver Creek.
"There's a plant rating, and that's what the 3 to 4.25 is," Latta explained. "Then there's a wet weather rating, which is your hydraulic capacity at the plant. The hydraulic capacity is limited to about 10 mgd, and we need to get to 22 mgd."
The overall recommendation from Jones & Henry Engineers is to expand the plant, replace outdated equipment and add a third oxidation ditch and two new clarifiers. This would eliminate the bypasses and enhance overall capacity, according to wastewater treatment plant superintendent Kerry Duncan.
"I think it's important to add here that … we are near capacity anyway, and the capacity increase allows Celina to grow economically by providing services for customers," he said. "It's hard to grow when you don't have the capacity to treat."
Latta also noted that the Ohio EPA had said it's going to be looking at the plant's permit limits on pollutants discharged into Beaver Creek.
"Permit limits are set based on the stream that you discharge to, and they're not certain if we increase your flow what that does to the stream water quality, and so they're looking at maybe keeping your loadings to the stream, which means that you have to treat to a little higher level of quality to be able to discharge," he said.
Latta believes that the prescribed improvements would enable the wastewater treatment plant to reach that higher level of effluent quality but cautioned that he doesn't know what type of limits Ohio EPA plans to set.
"In which case there is a possibility that we could end up having to add some tertiary treatment … on the back end to help further refine the process before it goes to the stream," he said.

Moving forward
If contracted further, Jones & Henry would launch the preliminary design phase.
"What we've proposed is starting out with preliminary design, which is taking the No Feasible Alternative report and advancing it, putting a lot more thought into it and refining the alternatives that we selected in the report and starting to build the design out of that," Latta said. "We'll take that and begin to analyze equipment selections, start to size some of the equipment and looking at what the improvement project is going to look like, come up with a better estimate for the project."
Under the revised project schedule, a permit to install for the planned improvements must be filed by Oct. 1, 2026, following by the initiation of construction on April 1, 2027, and completion of construction on April 1, 2029.
Asked about potential funding sources, Latta said a quick analysis revealed there's only a handful of programs for which the city would qualify.
"Because it is need-based and then there's also compliance," Latta said. "You've got the compliance side but you're a strong community which unfortunately works in your disfavor."
The Ohio EPA's WPCLF is likely the city's best bet, he said.
"As you're aware of, most likely, the wastewater department doesn't have a debt obligation currently. We paid off our debt obligation," Duncan said. "So that's a good thing going into a massive project like this."
City safety service director Tom Hitchcock said the city has been saving money but doesn't have enough to fund such a large-scale endeavor.
Subscribe for $17/month
Councilors took no action at the conclusion of the commitee meeting but indicated they will resume discussion at future meetings. Council meets next at 7 p.m. June 23 in council chambers on the second floor of the city administration building.
Additional online story on this date
Magoto's work pays off with trip to state, appointment to West Point
When talking about Louis Magoto after his second no-hitter of the postseason in Friday's 3-0 win over Montpelier in the regional final, Minster coach Mike Wiss talked about his pitcher's discipline. [More]
Subscriber and paid stories on this date
MARIA STEIN - Experts continue to assess the integrity of the remaining walls of the burned out St. John the Baptist Church, while a number of holy items have been retrieved from areas of the structure, which was badly damaged when a blaze erupted on the afternoon of May 29.
WAPAKONETA - May was a quiet month for communicable diseases in Auglaize County, with the community logging only two COVID-19 outbreaks, Director of Nursing Jessica Whetstone told county board of health members at their regular meeting on Tuesday morning.
SIDNEY - As part of the Ohio Department of Transportation's statewide re-imagined rest area project, the I-75 north and southbound rest areas in Auglaize County will close Monday, July 7, for a full replacement.
CELINA - Two people were arrested in Celina for possession of methamphetamine in separate traffic stops within two hours of one another on Monday.
CELINA - A 35-year-old Coldwater man was sentenced to nearly five years in prison on Tuesday for reportedly possessing more than half a pound of methamphetamine in both liquid and solid form, then failing to appear in court as required.
Minster Baseball Hospice Night, a charity baseball game held at Minster's Melcher Street Park May 9, was a huge success this year, according to a new
Division VII State Baseball Semifinal Preview
One of the main things Mike Wiss has stressed when talking about his upcoming opponent in the Division VII state baseball semifinals on Thursday is that this is not the same Russia squad the Wildcats defeated back in April.
Grand Lake Fishing Report
Good day everyone. I hope everyone is doing great.
So many things going on in and around the lake. Now is the time to take in all the events.
I
Compiled By Gary R. Rasberry
Celina plated three runs in the top of the eighth inning to pick up a 4-1 victory over New Bremen in ACME baseball action on Tuesday in Auglaize County.
2025 Division III Girls State Track and Field Champions
Cavalier State Qualifiers:
Kiersten Keller, Senior
• Champion, 4x400-meter relay
• Fifth place, 4x100-meter relay
• State qualifier, 4x2