Thursday
85°
Chance Thunderstorms
30%
Thursday Night
72°
Chance Thunderstorms
33%
Friday
83°
Chance Thunderstorms
44%
Friday Night
69°
Thunderstorms Likely
58%
Saturday
83°
Slight Chance Thunderstorms
24%
Saturday Night
64°
Slight Chance Thunderstorms
26%
Sunday
82°
Slight Chance Thunderstorms
18%
Sunday Night
63°
Partly Cloudy
10%
Monday
84°
Chance Thunderstorms
33%
Monday Night
66°
Chance Thunderstorms
54%
3 Day
Extended
Tuesday, October 17th, 2006

Something to be thankful for on Touvelle Street

By Timothy Cox

Work continues on Touvelle Street in Celina on Monday. The $1.2 million reconstr. . .

The $1.2 million reconstruction of Touvelle Street remains on schedule to wrap up around Thanksgiving.
All underground utility work is complete, most curbs and gutters are built and paving should begin next week, city development consultant Kent Bryan said. Even the recent bout of sharply cooler weather has not knocked the project off schedule, he said.
There was some concern the project would not be able to be completed this year when snow started flying last week. But Bryan said there still are several more weeks before asphalt plants close for the season and contractors need only a few mild days to get the paving done.
"The old rule of thumb has always been Thanksgiving," Bryan said. "Rarely do asphalt plants close before Thanksgiving and often they are open a couple of weeks into December, depending on the weather."
When the project was in the planning stages, city officials had anticipated that the final coat of asphalt would not be laid down until next spring. But Tumbusch Construction, St. Henry, the low bidder for the contract, insisted the paving be completed this season, Bryan said, and city officials didn't argue the issue.
The project includes complete reconstruction of the road surface and all curbs, gutters and sidewalks between Main Street and Fairground Road. Some of the new sidewalks are six feet wide instead of four in places where there was enough right-of-way for the wider paths. A water main underneath the street also is being replaced.
New decorative street lights also are being installed along the stretch. The black poles look nicer than the existing lights but are not the same type of poles used on the recent Ash Street reconstruction. The Ash Street poles cost about $2,500 each while the poles being used on Touvelle Street cost just $500, Bryan said.
City officials plan to use the more expensive poles only in the downtown district, he said.
The Ohio Department of Transportation is covering 80 percent of the street portion of the work. The city also secured Ohio Public Works Commission funding and committed some local money to the project.
Additional online story on this date
FINDLAY - Given the conditions, the Celina Bulldogs went all out to make sure their Division I boys soccer sectional would not need more than 80 minutes of regulation play. [More]
Subscriber only stories on this date
St. Henry school levy sought
Running wild in Auglaize
Classified union employees reach contract agreement
Fort Recovery officials to hire new police chief
Parking ordinance being addressed by city council
Two ticketed for using red-dyed diesel fuel in trucks
Who's in, who's out a little clearer this week