a_d
Tuesday, October 17th, 2006
By Timothy Cox
Something to be thankful for on Touvelle Street
  The $1.2 million reconstruction of Touvelle Street remains on schedule to wrap up around Thanksgiving.
All underground utility work is complete, most curbs and gutters are built and paving should begin next week, city development consultant Kent Bryan said. Even the recent bout of sharply cooler weather has not knocked the project off schedule, he said.
There was some concern the project would not be able to be completed this year when snow started flying last week. But Bryan said there still are several more weeks before asphalt plants close for the season and contractors need only a few mild days to get the paving done.
"The old rule of thumb has always been Thanksgiving," Bryan said. "Rarely do asphalt plants close before Thanksgiving and often they are open a couple of weeks into December, depending on the weather."
When the project was in the planning stages, city officials had anticipated that the final coat of asphalt would not be laid down until next spring. But Tumbusch Construction, St. Henry, the low bidder for the contract, insisted the paving be completed this season, Bryan said, and city officials didn't argue the issue.
The project includes complete reconstruction of the road surface and all curbs, gutters and sidewalks between Main Street and Fairground Road. Some of the new sidewalks are six feet wide instead of four in places where there was enough right-of-way for the wider paths. A water main underneath the street also is being replaced.
New decorative street lights also are being installed along the stretch. The black poles look nicer than the existing lights but are not the same type of poles used on the recent Ash Street reconstruction. The Ash Street poles cost about $2,500 each while the poles being used on Touvelle Street cost just $500, Bryan said.
City officials plan to use the more expensive poles only in the downtown district, he said.
The Ohio Department of Transportation is covering 80 percent of the street portion of the work. The city also secured Ohio Public Works Commission funding and committed some local money to the project.
Additional online stories for this date
Print and E-Edition only stories for this date
• St. Henry school levy sought
• Running wild in Auglaize
• Classified union employees reach contract agreement
• Fort Recovery officials to hire new police chief
• Parking ordinance being addressed by city council
• Two ticketed for using red-dyed diesel fuel in trucks
• Who's in, who's out a little clearer this week
a_d
Wednesday
82°
Chance Thunderstorms
48%
Wednesday Night
71°
Chance Thunderstorms
46%
Thursday
86°
Chance Thunderstorms
29%
Thursday Night
67°
Chance Thunderstorms
30%
Friday
82°
Partly Sunny
10%
Friday Night
63°
Partly Cloudy
6%
Saturday
84°
Partly Sunny
6%
Saturday Night
67°
Slight Chance Thunderstorms
19%
Sunday
86°
Chance Thunderstorms
29%
Sunday Night
68°
Slight Chance Thunderstorms
20%
Monday
85°
Chance Thunderstorms
32%
Monday Night
67°
Partly Cloudy
24%
3 Day
Extended
a_d
a_da_da_d
video_logoOnline Video
Tuesday, July 26
index pict
Boat fire on Grand Lake
Saturday, July 23
index pict
Celina Lake Festival Parade time-lapse
camera_logo Photo Albums
Tuesday, August 23
index pict
Monday, August 22
index pict
Monday, August 22
index pict
Monday, August 22
index pict
Saturday, August 20
index pict