a_d
Sunday Night
41°
Mostly Clear
1%
Monday
71°
Mostly Sunny
5%
Monday Night
50°
Mostly Cloudy
3%
Tuesday
75°
Partly Sunny
6%
Tuesday Night
58°
Partly Cloudy
7%
Wednesday
80°
Mostly Cloudy
20%
Wednesday Night
57°
Thunderstorms Likely
59%
Thursday
67°
Chance Thunderstorms
56%
Thursday Night
49°
Chance Thunderstorms
39%
Friday
70°
Chance Thunderstorms
41%
Friday Night
55°
Thunderstorms Likely
62%
3 Day
Extended
a_d
a_d
Tuesday, September 25th, 2007

Electricity plant could close down

Officials debate fixing expensive turbine

By Janie Southard
ST. MARYS - City officials are questioning whether to repair again a problem turbine at the city power plant or to simply shut down the plant.
This turbine unit is staffed and coal-fired, according to Electric System Superintendent Jerry Wolfe. Thus, operating this unit involves several city employees.
"That unit provides an average of 20 percent of the city's electric. It's not working now and hasn't for 300-plus days in the last couple years ... (What we do is) purchase electric from other sources," Wolfe said following Monday night's city council meeting.
Repairs could not be accomplished until at least March 2008 to the power source that continues to be the most expensive for the city.
Notes of the recent electric committee meeting presented to council Monday night indicate an estimated $250,000 for repairs with an insurance deductible of $100,000. The question then arises would the city be able to obtain more insurance on the unit, which was purchased new in 1967.
A recent talk with the city's insurance agent stressed there is no guarantee that company's insurance coverage would be available for the plant.
Off line 379 days in the past two years, the turbine has been on the long-term schedule to be shut down anyway in 2013.
With minimum maintenance until 2013 estimated at $500,000 and total cost to operate the plant for the next six years an estimated $970,000, Councilman Mike Kleinhenz stated that money would be better spent toward new equipment.
City Service Safety Director Tom Hitchcock compared buying new or used equipment, saying his observation is that the city hasn't had very good luck with used equipment.
"Everything he's seen that was purchased used seems to bring problems with it," according to the committee minutes.
However, the greatest concern, given the unit's recent history of breakdowns, is safety of the personnel in that location. And, should the plant be shut down, would those employees be out of a job?
No, they would be transferred to other city departments, according to Mayor Greg Freewalt.
In other business, the city will go out for bids today for construction of the new wastewater treatment plant, which could begin next year. Engineer's estimate for the construction is $12 million.
a_d
Additional online story on this date
ELIDA - Just like usual, the Celina girls soccer team went through its traditional postgame rituals after Monday's 1-all match at Elida.
The handshake line with Elida players, the two teams praying at the midfield circle, and the team meeting after the game. [More]
Subscriber only stories on this date
Boathouse will be built for emergency services
Celina council pays for water project design
The cost of workers' comp coverage to double next year
Condition changed to fair
Meeting with OEPA successful
Celina's tie against Elida is almost like a win
Tigers win sets up big matchup Thursday